According to different needs, submersible pumps also have many bai classifications. Tianjin Aote Pump Industry has deep well submersible pumps, submersible sewage pumps, submersible axial flow pumps, large submersible electric pumps, hot water submersible pumps, stainless steel submersible pumps, submersible screw centrifugal pumps, etc .
Acceptance of deep well submersible pumps
Handling
Inspection steps before the whole unit goes down the well
On-site assembly steps when the pump is transported separately
Check the water pump when the pump is split
Deep well submersible pump
Cable binding
Control and start of the unit
Overload, overcurrent, phase loss, short circuit, sensitivity adjustment
The user should carefully check and accept the cable sheath for damage when picking up the goods from the logistics company. Whether the pump is broken.
The loading and unloading truck should be careful to avoid damaging the concentricity of the unit or breaking the cable insulation.
A. Disassemble the filter, and use the pry bar to turn the coupling to rotate flexibly.
B Put the electric pump upright and fill with clean water, connect the cable connector, soak the connector at the water basin, and measure the resistance of the connector to ground The insulation resistance to water) value is not less than 500 megohms.
C. Place the pump upright and add detergent powder to the pump outlet with a suitable container. At the same time, slightly click the motor start button to carefully observe the direction of the pump. The time should not exceed 2 seconds. Make the consecutive marks.
A. Put the motor vertically upright before installation, open the vent hole and the water injection hole, pay attention to open both water plugs, tighten the water injection plug and the water plug with full water, and observe whether the motor is leaking. Don't go down the well. The reason may be that you bumped into it during the transportation process. You should contact the agent or manufacturer in time to negotiate and solve it until it is leak-proof (observe 10-15 minutes). Then measure the insulation resistance of the motor, its value is not less than 50 megohms.
B. Wrap the cable connector. After wrapping, try the direction of the motor. Check whether the direction of the motor is consistent with the direction of the arrow marked on the water pump, and make the successive marks.
A. Remove the upper shell of the pump to expose the top impeller,
B. Turn the impeller by hand to see if it is flexible
C. Pull the impeller in the direction of the pump axis to observe the total amount of impeller seven times (general QJ pump 4-6 mm) The installation coupling is integrated with the motor so that the motor shaft head and the water pump shaft head are tight and no gap is allowed.
E. Looking at the clearance between the impeller and the runner, it should be in the middle of the total tunnel (allowable deviation ±0.5mm).
F. When the deviation is greater than 0.5 mm, use the adjustment shim to adjust to the middle position and rotate the impeller by hand should be flexible.
G. Then drill the top screw hole of the coupling, tighten the top screw to install the upper shell.
H. Turn the coupling once again with a crowbar to rotate flexibly to pass the assembly. Then install the filter and the wire protection box.
Before going down the well, use a rope to hang a log or steel pipe with the same length of the unit (the diameter is equal to the maximum outer diameter of the unit) to test whether the well pipe is straight. To avoid jamming the unit when going down the well.
The cable should be tied to the water pipe with an insulated cable tie, and no metal wire.
Selection of control equipment. Motor power × 1.2-1.4 times = control cabinet power. The control cabinet shall have protection measures such as phase loss, overload, overcurrent and short circuit. After the downhole installation is complete, start the test machine. The startup time is between 10-25 seconds according to the difference in motor power. The startup time of the high-power motor should be relatively long. Check whether the current is overloaded and whether the three-phase current is balanced. Make a record. And feedback the manufacturer as the basis of warranty.
This step is very important, please installer carefully debug.
A. Overload and over-current debugging: Turn the current adjustment knob of the thermal relay slowly to a direction smaller than the actual working current, and rotate a little scale each time, with an interval of about 2-5 minutes, until the thermal relay action unit stops working. Then rotate the scale a little in the reverse direction.
B. Phase-deficient sensitivity debugging: restart the unit, and disconnect the fuse of the knife switch of the unit one by one to make the unit in two-phase electrical working state. Observe whether the thermal relay can cut off the control power within 5 seconds.
C. Short circuit test: This step is usually protected by the air switch of the power supply system. Generally, no on-site test (more dangerous) requires that the power supply system must be equipped with an air switch (the air switch model is preferably DW10, and the second choice is DZ). Shanghai Submersible Pump Co., Ltd. specializes in submersible series products such as sewage and submersible pumps, sewage pumps, deep well pumps, water mixers, pipeline pumps, etc., without negative pressure, voltage regulation, pressurized complete water supply equipment, sewage lifting device, pressurized A manufacturing enterprise that manufactures and researches pumps and vertical multistage pumps. Products focus on practicality, innovation, environmental protection, economy and efficiency.